Journal of Cleaner Production 257, 120527
Abstract: Precast concrete structures (PCs) are widely used in the construction industry to reduce project delivery times and improve quality. On-time delivery of PCs is critical for successful project completion because the processes involving precast concrete are the critical paths in most cases. However, existing models for scheduling PC production are not adequate for use in dynamic environments where construction projects have uncertain construction schedules because of various reasons such as poor labor productivity, inadequate equipment, and poor weather. This research proposes a dynamic model for PC production scheduling by adopting a discrete-time simulation method to respond to due date changes in real time and by using a new dispatching rule that considers the uncertainty of the due dates to minimize tardiness.
Authored by: Taehoon Kim, Yong-Woo Kim, and Hunhee Cho